CONSTRUCTION REPORT - WEEKLY
CONSTRUCTION REPORT - WEEKLY
Owner: Shawanaga First Nation
Project: Water Supply System Upgrade
Location: WTP on Village Road, 1.6 km from West Gate
Contractor: Cecchetto and Sons Ltd.
Week Ending Date. Feb-7-25
Inspector: Tony Kocis
This weekly report covers the week starting Feb. 3rd to Feb. 7th, 2025 for the new Water Treatment Plant.
- Cecchetto carpenter and labourers installed the 6" curb around the 8" drain in the southwest corner of the process room. Cecchetto also backfilled the open excavation in the existing distribution center to allow Lopes Mechanical to complete new underground plumbing.
- JTM Tower Specialist returned to site to install both the communication and cell booster cable and have also installed the Omni Antenna for cell booster.
- Lopes Mechanical continue with installing analog gauges, air release devices and piping drains throughout the process room of the New WTP building.
- Nor-Tech continue to pull wire from the PLC cabinet to the process room and completing connections of the various equipment in the process room. Nor-Tech also continues to pipe conduit to the individual devices in the process and pulling wire to these devices.
mni antenna for cel booster
Cecchetto formed, poured, and stripped the concrete curb around the 8" backwash JTM Tower Specialist returned to site to install both the communication and cell drain to the sedimentation tank out of the southwest corner of the new WT
booster cable on the two new communication towers. One at the existing distribution
building.
center and the other at the new WTP plant. JTM has pulled the cables and have
installed the cel hooster antenna on both towers
Cecchetto installed -fill .4 pa concrete at the existing distribution center for new septic
Nor-Tech Power continue to run conduit both hard pipe pvc and and flex pipe to the
system connection to allow Lopes Mech. To complete underground plumbing as part of the retro indvidual devices in the process room. Nor-Tech also pulled wire from the PLC cabinet to the fit upgrade to the existing distribution center. Lopes also continues with installation of air
junction boxes along the south wall of the process room and continue to terminate
releases and piping drains throughout the process room of the new WT building.
complete the connection of the devices and analver panels also along the south wall